Laboratory Report #4
Cost Estimating
A&CSM 520
October 31, 2002
Due: November 5, 2002
Unit costs for different types of buildings and site development.
a. Office - $70/square foot
b. Manufacturing “A” -- $100/square foot
c. Manufacturing “B” -- $200/square foot
d. Warehouse -- $55/square foot
e. Site Development -- $80,000/acre
In addition to the construction costs, there are the following costs:
a. Design fees at 9% of construction costs
b. Construction manager fee at 1.5% of the construction costs
c. Permits and inspections at $25,000
d. Planning contingency at 3% of construction and design costs
e. Construction contingency at 5% of construction costs